2020 Sidewalk Plan Per your request the Public Works Department has completed the following sidewalk plan for submission to the City Council. The sidewalk plan consists of three major components as follows: 1. Sidewalk Rehabilitation During the budget process it was determined to shift funds from new sidewalk construction to repair and maintenance in order to bring the existing sidewalk within the City to a safe and functional condition. Maintenance Forman Marvin Roberts has completed a survey of existing sidewalks and has identified approximately 1,165 liner feet of sidewalk that requires replacement. In some areas with curb and gutter the replacement will need to include replacement of the curb and gutter as well. The list of repairs needed is as follows: PRIORITY I SW 6TH STREET (500 BLK) South side 5’x10’ Drain Box SW 6th STREET (300 BLK) South side 5’x30’ SW 6TH STREET (400 BLK) North side 5’x50’ SW 12th STREET (100 BLK) 5’x30’ SW 3rd AVE (800 BLK) 30’x5’ SW 3rd AVE (900 BLK) 5’x30’ SW 8th STREET (100 BLK) 5’x10’ SW 6th STREET (100 BLK) 5’x60’ SW 7th STREET (100 BLK) South side 50’x5’ North side 15’ SW 4th AVE (200 BLK) East side 315 South driveway 20’ SW 2nd STREET (400 BLK) Smitty’s Glass 80’x10’ SW 2nd AVE (200 BLK) East side 5”x10’ West side 5’x20’ SW 2nd AVE (300 BLK) 20’ SW 2nd AVE (400 BLK) West side 10’x5’ wide SW 3rd AVE (1100 BLK) West side 5’x10 SW 3rd AVE (1300 BLK) 70’ SW 3rd AVE (1400 BLK) 35’x5’ SW 3rd AVE (1400 BLK) add 30’ SW 3rd AVE (1900 BLK) 4’x40’ NW 4th STREET (400 BLK) South side 5’x10’ NW 5th STREET (400 BLK) North side 5’x30’ SE Park STREET (100 BLK) North side 5’x10’ SE 2nd AVE (100 BLK) 5’x10’ SE 3rd AVE (100 BLK) 5’x20’ To: Marcos Montes De Oca From: David Allen Date: 2/6/2020 Re: Public Works 2020 Sidewalk Plan PRIORITY II SW 5th AVE (700 BLK) 5’x45’ SE 8th AVE (100 – 200 BLK) 140’x4’ 1108 SE 8th AVE 4’x5’ 1301 SE 8th AVE 4’x15’ 1305 SE 8th AVE 4’x20’ SW 2nd AVE (200 BLK) East & West side Storm Drain 30’, East side West side 15’ SW 2nd AVE (900 BLK) between 912-914 West side 22’ 807 SW 2nd AVE (800 BLK) East side 5’x50’ SW 6th STREET (100 BLK) Remove cedar tree and stump, leave rock SW 2nd AVE (600 BLK) curb and road, need to cut tree roots replace curb NW 3rd STREET 7.5’x5’ NW 3rd STREET 5’x15’ NW 3rd STREET 5’x10’ NW 3rd STREET 5’x15’ NW 5th AVE & 3rd STREET (Corner) 5’x15’ NW 2nd AVE (100 BLK) West side 5’x25’ NW 4th STREET (100 BLK) South side 5’x50’ NW 4th STREET (100 BLK) South side 5’x20’ NW 5th STREET (400 BLK) North side 5’x30’ NW 5th STREET (200 BLK) curb & driveway 5’x5’ NW 5th STREET (300 BLK) 12’x5’ NW 4th AVE (300 BLK) East and West side 5’x60’ NW 4th AVE (300 BLK) West side curb sinking NE 6th STREET (400 BLK) 5’x20’ NE 7th AVE (100 BLK) 5’x15’ NE 3rd AVE (200 BLK) 5”x20” NE 3rd STREET North side 5’x20’ 2. New Construction Two (2) new construction projects have been identified. The primary project is 1,000 linear feet of sidewalk on SE 6th Avenue connecting Centennial Park with the existing sidewalk on SE 4th Street. This segment will complete access to the new park from all blocks of the surrounding neighborhood. The right of way on SE 6th Avenue is insufficient for the construction of the new sidewalk. The City will need to obtain an easement from the eleven (11) property owners on the East side of SE 6th Avenue for this project to be completed. SE 6th Avenue Sidewalk Project A secondary project has been identified which can be completed in this year. If for some reason the primary project cannot be completed. This project, located on SW 8th Avenue and SW Park street will connect the new apartments to be constructed south of SW 8th Avenue with the downtown area allowing the residents of the 190 unit project to walk to the downtown businesses. SW 8th Avenue Sidewalk Project Potential Future Projects: • NW 2nd Street, Extend existing sidewalk from NW 10th Ave to NW 11th Ave. • SW 6th Street, Extend existing sidewalk from SW 10th Ave to existing sidewalk on SW 11th Ave • SW Park Street, Extend existing proposed new sidewalk at SW 8th Avenue to existing sidewalk on SW 11th Avenue • SE 8th Street, Connect existing sidewalk on SE 8th Avenue to existing sidewalk on SE 9th Avenue • NE 3rd Street, Connect existing sidewalk at NE 4th Ave to existing sidewalk on NE 7th Avenue 3. ADA Ramp Construction To meet current access requirements, additional ADA ramps are required in the downtown area as well as the reconstruction of some of the existing ramps in order for them to meet current standards. It is proposed that ADA sidewalk ramp along with an ADA parking space be installed mid-block on each side of South Park street in order to meet ADA requirements. A survey of Southeast and Southwest Park streets has identified a total of 30 ADA ramps are required. In the future, additional ramps should be constructed mid-block on the side streets connecting to South Park Street where parking exists for business access. The current sidewalk bid being processed includes ten (10) ramps to be constructed starting in the 100 block of SW Park street. An additional four (4) ramps will be included in the FDOT SCOP funded projects on SE 3rd Ave and SW 5th Avenue. Additional ramps will be included over the next 2-3 years until the downtown area is completed. CR-BCR-L CR-L City of Okeechobee S Park Street ADA Ramp Installation East 200 Blk Not To Scale CR-L CR-L CR-L CR-A CR-B City of Okeechobee S Park Street ADA Ramp Installation East 100 Blk Not To Scale CR-B CR-A CR-L City of Okeechobee S Park Street ADA Ramp Installation West 100 Blk Not To Scale CR-BCR-L CR-L CR-A City of Okeechobee S Park Street ADA Ramp Installation West 200 Blk Not To Scale CR-BCR-L CR-L CR-A City of Okeechobee S Park Street ADA Ramp Installation West 300 Blk Not To Scale CR-B CR-L CR-A City of Okeechobee S Park Street ADA Ramp Installation West 400 Blk Not To Scale CR-L CR-LCR-L CR-B City of Okeechobee S Park Street ADA Ramp Installation West 500 Blk Not To Scale CR-LCR-L CR-B CR-A City of Okeechobee S Park Street ADA Ramp Installation West 600 Blk Not To Scale